first_imgWork to be completed in the week of Oct. 1-5:·   Feriozzi Concrete will continue work on Sixth Street between West Avenue and Bay Avenue restoring curb gutter and sidewalks.·   Pipe crews will continue installing main on Seventh Street, working from Bay Avenue to West Avenue. ·   Paving crews will continue paving from Second Street to Fifth Street between West Avenue and Bay Avenue.·   Mayor Jay Gillian said the contractor paved Fifth Street this week. The completion of Fifth Street comes in time for Saturday’s Bike MS: City to Shore Ride, which ends on Fifth Street.·   Weather permitting, crews will pave Third Street starting Monday and continue work between Second Street and Fifth Street during 10-hour days Monday through Thursday.Project DesignSee Design Presentation for Detail Fifth Street has been repaved in time for Saturday’s Bike MS: City to Shore Ride fundraiser.Concrete work is in progress on Sixth Street. Third Street is still a work in progress for the drainage project. last_img read more